Expert advice in minutes not days. Register it's free and ask your first question now.
ReachBack is a free community help desk for construction professionals run by Built Intelligence. A library of high-quality questions from real users with answers delivered and curated by industry experts.

5,008 questions

5,336 answers

1,102 comments

Register its Free

Download here

NEC4 ECC Option C - Inspection of records of Defined Cost

+1 vote
95 views
Under clause 50.9, where the Contractor notifies the Project Manager when a part of the Defined Cost has been finalised to allow inspection of such records, what is meant by "a part of Defined Cost"?

Does this allow the Contractor to introduce intervals at it's own discretion, at monthly or quarterly intervals, or does this mean the Defined Cost associated with a part of the Works that has been finalised?

Also, does this mean that once a "part of the Defined Cost" has been accepted or assessed by the Project Manager, it cannot be revised? i.e. in the same way as an implemented Compensation Event.
asked Jan 23 in Payment by philjbrady (770 points)  

1 Answer

+2 votes
 
Best answer
It is deliberately defined a bit vaguely because what is appropriate will vary from contract to contract : it could be by work type, by subcontract, by cost classification e.g. staff costs or, as you allude to, by time. Regardless, it as the Contractor chooses.

You are correct in that once it has been accepted or assessed, it cannot be revised, except via the disputes mechanism.
answered Jan 23 by Jon Broome (53,290 points)  
selected Feb 6 by philjbrady