Expert advice in minutes not days. Register it's free and ask your first question now.
ReachBack is a free community help desk for construction professionals run by Built Intelligence. A library of high-quality questions from real users with answers delivered and curated by industry experts.

4,952 questions

5,279 answers

1,043 comments

Register its Free

Download here

NEC ECS: Can Liquidated Damages be taken from Retention?

0 votes
84 views
Following an error, the only amount due to a Subcontractor is their retained 5%. They are due to pay liquidated damages as they were late against 2 sectional completion dates.

Can the liquidated damages amount be deducted from the retention? So on the Payment Certificate, release 2.5% to them but then deduct the DD's from that?
asked Jan 17 in Secondary X, W and Y options by WatersideSurveyor (660 points)  

1 Answer

+1 vote
 
Best answer
Yes, that is what the retention is for.
answered Jan 17 by Rob Horne (19,440 points)  
selected Jan 22 by WatersideSurveyor