NEC TSSC: Termination

0 votes
139 views
TSSC clause 90.1 states “if either party wishes to terminate the Contractor’s obligation to Provide the Service, he notifies the other Party giving details of his reason for terminating.”

If the Employer proposes to terminate for Reason 5 (any other reason) does any further detail on the reason need to be given or is using the term “any other reason” all that is required?
asked Jan 7, 2019 in Termination by Zarniwoop (150 points)  

1 Answer

+1 vote
 
Best answer
Whilst it would be good practice for the Employer to explain the reason in more detail than just quoting the term "any other reason", strictly the contract doesn't require this. Technically the Employer might be in breach of clause 10.1 i.e. absence of a detailed explanation of the reason is a failure to co-operate effectively with the Contractor, however this argument doesn't really take you anywhere from a commercial point of view.

The only other argument I could think of would be to claim the Employer's termination isn't in accordance with the contract (but as already discussed, is it really?) and that it amounts to repudiation. Again though this doesn't take you to a better place commercially and the contract won't become un-terminated.

Remember that because the Employer chose reason 5 you will recover "5% of any excess of a forecast of the amount due ..." which is intended to be a sweetener for the inconvenience you've been caused as you weren't in breach of contract.
answered Jan 8, 2019 by Neil Earnshaw Panel Member (30,260 points)  