Expert advice in minutes not days. Register it's free and ask your first question now.
ReachBack is a free community help desk for construction professionals run by Built Intelligence. A library of high-quality questions from real users with answers delivered and curated by industry experts.

4,959 questions

5,287 answers

1,051 comments

Register its Free

Download here

NEC ECC: Employer use and takeover

0 votes
149 views
If an employer uses part of a building prior to completion to suit a Contractor's method of working Cl35.2., does a Take Over certificate need to be issued?
asked Dec 21, 2018 in General by charlotteking (350 points)  

2 Answers

+1 vote
The short answer is 'No'.

The justification is that clause 35.2 states :"
The Employer may use any part of the works before Completion has been certified. If he does so, he takes over the part of the works when he begins to use it except if the use is
- ...
 to suit the Contractor’s method of working."

So from what you have said, the Employer has therefore not taken it over.

Therefore, under clause 35.3, the PM should not certify take-over.
answered Dec 21, 2018 by Jon Broome (52,410 points)  
0 votes
Just to add to Jon's correct answer, the reason why 'take over' is certified by the PM is that it could lead to further contractual actions and rights, including a CE under 60.1 (4), termination under 91.6, transfer of risk/liability under 80.1 and delay damages obligations under X7.
answered Jan 2 by Andrew W-I (17,070 points)