NEC ECS: Who pays for the costs of correcting defects under Option B?

0 votes
201 views
We have raised a defect on the subcontractor.  The levels are incorrect on some blockwork., leaving the openings too wide.  I understand they get paid for the initial work but who stands the costs of repairing the defect?
asked Dec 19, 2018 in Testing and Defects by shazgal (130 points)  

2 Answers

+1 vote
On an Option B, the Subcontractor should correct at its own costs.
answered Dec 20, 2018 by dave bates (12,800 points)  
0 votes
Under option B the Contractor is paid in accordance with completed items on their activity schedule. Therefore if they do one thing twice, there is only a mechanism to get paid once so therefore the Contractor pays for correcting their own defects. This is the same principle for option A.
answered Dec 21, 2018 by Glenn Hide (72,800 points)