The Employer or Others have not worked within the times shown on the Accepted Programme. Is this a compensation event?

+1 vote
338 views

The Employer or Others have not worked within the times shown on the Accepted Programme. Is this a compensation event?

asked Oct 10, 2012 in Compensation Events by BuiltIntelligence (870 points)  

1 Answer

+1 vote
 
Best answer

This is a compensation event (see Clause 60.1(5)). The Contractor notifies the Project Manager of the event as a compensation event.

answered Oct 10, 2012 by BuiltIntelligence (870 points)