Expert advice in minutes not days. Register it's free and ask your first question now.
ReachBack is a free community help desk for construction professionals run by Built Intelligence. A library of high-quality questions from real users with answers delivered and curated by industry experts.

4,869 questions

5,183 answers

969 comments

Register its Free

Download here

NEC ECC: Repairs to temporary works

0 votes
59 views
An area of temporary works have been constructed under an NEC Option C Contract.  There have now been a couple of instances where weather (but not outside of the 10 year average) has damaged the temporary works.  Does the Contractor have the obligation to maintain/repair the temporary works or would this constitute a CE under the contract ?
asked Dec 4, 2018 in Compensation Events by LFS (140 points)  

1 Answer

0 votes
That would be a Contractor risk - and no where under clause 60.1 that the Contractor would be able to notify that as a compensation event I suggest.
answered Dec 4, 2018 by Glenn Hide (68,990 points)  
Or more precisely, a risk within the target Prices and, because it is a target cost contract with pain/gain, a shared risk.