NEC ECC: Repairs to temporary works

0 votes
115 views
An area of temporary works have been constructed under an NEC Option C Contract.  There have now been a couple of instances where weather (but not outside of the 10 year average) has damaged the temporary works.  Does the Contractor have the obligation to maintain/repair the temporary works or would this constitute a CE under the contract ?
asked Dec 4, 2018 in Compensation Events by LFS (140 points)  

1 Answer

0 votes
That would be a Contractor risk - and no where under clause 60.1 that the Contractor would be able to notify that as a compensation event I suggest.
answered Dec 4, 2018 by Glenn Hide Panel Member (87,060 points)  
Or more precisely, a risk within the target Prices and, because it is a target cost contract with pain/gain, a shared risk.