Expert advice in minutes not days. Register it's free and ask your first question now.
ReachBack is a free community help desk for construction professionals run by Built Intelligence. A library of high-quality questions from real users with answers delivered and curated by industry experts.

Do you want to update your skills in NEC3, NEC4, JCT, Procurement, CDM or Project management?

Sign up for one of our free online courses.

4,754 questions

5,050 answers

907 comments

Register its Free

Download here

NEC ECC: Repairs to temporary works

0 votes
43 views
An area of temporary works have been constructed under an NEC Option C Contract.  There have now been a couple of instances where weather (but not outside of the 10 year average) has damaged the temporary works.  Does the Contractor have the obligation to maintain/repair the temporary works or would this constitute a CE under the contract ?
asked Dec 4 in Compensation Events by LFS (140 points)  

1 Answer

0 votes
That would be a Contractor risk - and no where under clause 60.1 that the Contractor would be able to notify that as a compensation event I suggest.
answered Dec 4 by Glenn Hide (66,350 points)  
Or more precisely, a risk within the target Prices and, because it is a target cost contract with pain/gain, a shared risk.