Expert advice in minutes not days. Register it's free and ask your first question now.
ReachBack is a free community help desk for construction professionals run by Built Intelligence. A library of high-quality questions from real users with answers delivered and curated by industry experts.

4,864 questions

5,179 answers

966 comments

Register its Free

Download here

NEC ECC: For a project located in Edinburgh, Scotland, does the Housing Grants, construction and regeneration act 1996 apply?

0 votes
78 views
Should we include W1 or W2 in the NEC3 ECC contract?
asked Nov 29, 2018 in Secondary X, W and Y options by Rochelle (140 points)  

1 Answer

0 votes
The simple answer is YES the 'Construction Act' applies to England and Wales or Scotland, so you should use Option W2.

The main difference is that where the payment or adjudication provisions in the contract are not compliant wih the requirements of the 'Construction Act', then the Scottish equivalent of 'The Scheme for Construction Contracts' would apply.
answered Nov 29, 2018 by Andrew W-I (15,030 points)