Expert advice in minutes not days. Register it's free and ask your first question now.
ReachBack is a free community help desk for construction professionals run by Built Intelligence. A library of high-quality questions from real users with answers delivered and curated by industry experts.

4,952 questions

5,279 answers

1,043 comments

Register its Free

Download here

NEC ECC: Option A labour rates

0 votes
106 views
Hi my end client has challenged unskilled labour rate being applied to our direct labour who are travelling and subsiding for the project. There is no agreed rates for unskilled labour in the contact or rates. The client has paid these rates previously however is making its own assessment of the rate that should be applied. What rights do I have to challenge the (contractor) rate applied and the (client) rate been proposed for the labour?
asked Nov 1, 2018 in General by positivethinker (140 points)  

1 Answer

0 votes
I would turn this question around : what right do they have to challenge the rates you have put forward for direct labour ?

If you have built up the rates in accordance with the Shorter Schedule of Cost Components and have presented that honestly, then their right is to seek justification e.g. "how did you arrive at that figure". My view is that NEC3 Shorter Schedule is a bit too brief when it comes to this and the Panel (as was) seem to agree as the Guidance Notes almost say "see the full schedule if this brief". (Don't get me started on the 4th edition Short Schedule for People which is even briefer !!!)

Nevertheless, if you have given an honest breakdown with sufficient justification, then they would not have the right to make their own assessment.
answered Nov 2, 2018 by Jon Broome (52,270 points)