WI hard-copy drawing references another drawing which has not been included in hard-copy. Is the referenced drawing included in the WI?

0 votes
171 views
The Works Information includes a hard-copy drawing, which references another drawing which has not been included in hard-copy.

Is the drawing referenced included into the Works Information?
asked Oct 30, 2018 in Legal and Disputes by TROY (120 points)  

1 Answer

+1 vote
I would say 'Yes' on the same basis that standard specifications are often referenced from the 'pack' given to the tendering contractors without the need to specifically forward them to the tendering contractors. Likewise, when the contract is signed.
answered Oct 31, 2018 by Jon Broome Panel Member (64,190 points)