General contract question: can application be submitted anyway?

0 votes
125 views
If a construction contract provides for no application for payment from the subcontractor, can he still submit one and it will become the default payment notice?
asked Oct 30, 2018 in Legal and Disputes by Community Manager (3,930 points)  

1 Answer

0 votes
Yes, the Subcontractor can submit one.

Yes, it POTENTIALLY becomes the default payment notice.
answered Oct 30, 2018 by Jon Broome Panel Member (64,190 points)