The Project Manager has given an instruction to stop or not to start any work or to change a Key Date. Is this a compensation event?

+1 vote
847 views

The Project Manager has given an instruction to stop or not to start any work or to change a Key Date. Is this a compensation event?

asked Oct 10, 2012 in Compensation Events by BuiltIntelligence (870 points)  

1 Answer

+1 vote
 
Best answer

This is a compensation event (see Clause 60.1(4)). The Project Manager has authority to instruct the Contractor to stop or not to start work (see Clause 34.1) and he may do this for safety or other reasons. He may also vary a Key Date (see Clause 14.3). The Contractor should notify the Project Manager of the event as a compensation event.

answered Oct 10, 2012 by BuiltIntelligence (870 points)