Expert advice in minutes not days. Register it's free and ask your first question now.
ReachBack is a free community help desk for construction professionals run by Built Intelligence. A library of high-quality questions from real users with answers delivered and curated by industry experts.

5,368 questions

5,743 answers

1,275 comments

Register its Free

Download here

NEC3: Design liability on Contractor proposed equipment/built elements

+2 votes
161 views
We are currently in the process of letting a main contract that includes MEP elements that are defined (effectively) by a performance specification. Naturally, the consultant has used a provisional equipment selection (that they will not share) to ensure design coordination and viability.

The Contractor is concerned that the lack of a named product, and the requirement to propose a product for acceptance constitutes "design", as they have made a choice. Meaning that if there were legal issues at a later date (for whatever reason) the design liability would sit with them.

The Consultants understanding is that once a piece of equipment has been accepted all responsibility for design sits with the consultant, with any issues regarding installation/workmanship sitting with the Contractor.

Which is correct?
asked Oct 10, 2018 in Risk and Insurance by Jasoncrozi (190 points)  

1 Answer

+2 votes
The Contractor is correct.
answered Oct 10, 2018 by Jon Broome Panel Member (60,240 points)