Expert advice in minutes not days. Register it's free and ask your first question now.
ReachBack is a free community help desk for construction professionals run by Built Intelligence. A library of high-quality questions from real users with answers delivered and curated by industry experts.

Do you want to update your skills in NEC3, NEC4, JCT, Procurement, CDM or Project management?

Sign up for one of our free online courses.

4,760 questions

5,056 answers

911 comments

Register its Free

Download here

NEC ECC: How is wind delay determined as a CE?

+1 vote
55 views
Within the contract the weather measurement is "the average wind speed per day".
We have obtained weather data which shows the monthly Mean Wind Speed (1 in 10 value) is 14 mph and the Mean Wind Speed for the month in question is 12 mph. Are we entitled to a CE for any days when the daily mean wind speed exceeds the 1 in 10 value?
asked Oct 10 in Compensation Events by Formwork18 (130 points)  

1 Answer

+2 votes
I will keep this brief - no it would seem not.

Wind is not normally a standard weather measurement and needs to be added in. Normally I would see it state "on days where it exceeds X for more than Y minutes" but the wording here suggests it has to have exceeded a monthly average before it is a compensation event - as on average it has not reached the 1 in 10 threshold.
answered Oct 10 by Glenn Hide (66,480 points)  
The data we obtained does give a daily average though, and this is the measurement in the contract, not monthly, but yes I admit it is not worded very well