What payments are made to the Contractor in a currency other than that of the contract?

0 votes
405 views

What payments are made to the Contractor in a currency other than that of the contract?

asked Oct 16, 2012 in Secondary X, W and Y options by BuiltIntelligence (870 points)  

1 Answer

0 votes
 
Best answer

The Contractor is paid in currencies other than the currency of the contract for items or activities listed in the Contract Data (see Clause X3.1).

answered Oct 16, 2012 by BuiltIntelligence (870 points)