Expert advice in minutes not days. Register it's free and ask your first question now.
ReachBack is a free community help desk for construction professionals run by Built Intelligence. A library of high-quality questions from real users with answers delivered and curated by industry experts.

Do you want to update your skills in NEC3, NEC4, JCT, Procurement, CDM or Project management?

Sign up for one of our free online courses.

4,654 questions

4,932 answers

850 comments

Register its Free

Download here

NEC ECC: Liability for an uncorrected Defect

+1 vote
87 views
I understand the principle behind clause 45 and that the PM "assesses" the cost of correcting a Defect but if the Employer decides to have a third party correct the Defect does this mean that the Contractor will no longer be accountable for that element of the work should a latent defect/issues appear at a later stage?

Obviously, the Contractor's argument will be should a latent defect/issue appear it is not his responsibility or fault and any issue is down to the work carried out by the third party.
asked Oct 2 in NEC3 Testing and Defects by john.james (160 points)  

2 Answers

0 votes
 
Best answer
This isn't really an NEC question as the answer would be the same in any contract. The Employer would need to prove that the latent defect was a Defect under your contract, i.e. that it was caused by your original works (e.g. part of the works not in accordance with the Works Information) and not by the works of the other contractor.
answered Oct 6 by Neil Earnshaw (17,190 points)  
selected Oct 6 by Glenn Hide
0 votes
It would depend on the cause of a possible Latent Defect.

If it is caused by workmanship or performance of materials then the Contractor could reasonably argue that it was the 'fault' of the Third Party.

If the Contractor had responsibility for Design, however, then that may be a different matter, depending also on whether there is a corresponding 'Fit for Purpose' or 'Reasonable Skill and Care' obligation.

The hard part, of course, would be proving whether it is one or the other.  For instance, a repair to a concrete structure by a Third Party may subsequently 'break up' again, although would you be able to determine whether it was caused by workmanship and/or choice of materials or whether the design of the structure didn't correctly apply and specified requirements for loading etc.
answered Oct 3 by Andrew WI (11,460 points)  
reshown Oct 6 by Glenn Hide