Our contract is Short Contract NEC3. There is a Price List containing quantities and rates for the Siteworks and Drainage Sections of the works only.
There are Z Clauses which deletes the Compensation Event Clause 60.1 (13) i.e. a difference between the final total quantity of work done and the quantity stated in the Price List can be altered as a CE.
With this Z Clause included in the contract, can the Client remeasure one particular item within the Siteworks section of the Price List because they know the quantity is high for that item?