On an NEC option A contract; the weather CE 60.1(13) has been removed from the contract but a CEN occurred which then pushed the earthworks operation out on the accepted programme from the summer months to winter months.
Now the original earthworks has now been delayed because of bad weather, Does this then warrant a CEN because?