Expert advice in minutes not days. Register it's free and ask your first question now.
ReachBack is a free community help desk for construction professionals run by Built Intelligence. A library of high-quality questions from real users with answers delivered and curated by industry experts.

5,053 questions

5,390 answers

1,132 comments

Register its Free

Download here

NEC ECC: How often do you have to submit a programme?

0 votes
112 views
This is to do with the NEC3 contract.
asked Sep 19, 2018 in Time by shelbybarclay00 (120 points)  

2 Answers

+1 vote
Your answer is in clause 32.2.

It is the interval stated in contract data as the minimum submission periods (typically every month or every four weekly) but the Contractor can submit one when ever they want in between times and the Project Manager can submit a revised programme when ever they want which the Contractor would have to submit within the period of reply (stated in contract data 1).
answered Sep 19, 2018 by Glenn Hide (72,800 points)  
0 votes
Normally, at the interval stated in Contract Data part 1 which is typically 4 weekly or monthly.

But, the PM can instruct a submission and the Contractor can choose to submit a revised one - see clause 32.2
answered Sep 19, 2018 by Jon Broome (53,640 points)