Expert advice in minutes not days. Register it's free and ask your first question now.
ReachBack is a free community help desk for construction professionals run by Built Intelligence. A library of high-quality questions from real users with answers delivered and curated by industry experts.

5,751 questions

6,168 answers

1,429 comments

Register its Free

Download here

The Employer has not provided something which he is to provide by the date for providing it shown on the Accepted Programme. Is this a compensation event?

+1 vote
355 views

The Employer has not provided something which he is to provide by the date for providing it shown on the Accepted Programme. Is this a compensation event?

asked Oct 10, 2012 in Compensation Events by BuiltIntelligence (870 points)  

1 Answer

+1 vote
 
Best answer

This is a compensation event. The Works Information should give details of anything, such as Plant and Materials, which the Employer is to provide and of any restrictions on when it is to be provided. The Contractor is required to include this information on the programme under Clause 31.2. The Contractor notifies the Project Manager of the event as a compensation event (see Clause 60.1(3) and Clause 61.3).

answered Oct 10, 2012 by BuiltIntelligence (870 points)