Expert advice in minutes not days. Register it's free and ask your first question now.
ReachBack is a free community help desk for construction professionals run by Built Intelligence. A library of high-quality questions from real users with answers delivered and curated by industry experts.

4,851 questions

5,167 answers

961 comments

Register its Free

Download here

NEC ECC: How would the PM make an assessment for a compensation event if... ?

0 votes
140 views
There is a case in Option C contract, the Contractor’s costs overall are far less than the Bill of Quantities rate but that the bill rates for the works are actually underpriced. As a Project Manager, how to make an assessment for a compensation event?

Thanks.
asked Sep 9, 2018 in Compensation Events by lok1708 (120 points)  

1 Answer

+1 vote
First off, under option C you would expect an activity schedule rather than a B of Q. Either way, under option A and C the Contractor takes the risk of errors in activity schedule, where as Employer takes risk in options B and D. This is option C, so any errors in that B of Q will be Contractor risk in terms of building up the original target Price.

As with any CE, it is assessed by building up a quotation in terms of the elements within the schedule of cost components. Only if both Parties agree do you use any rates or lump sums from activity schedule/B of Q and even then on a case by case basis.  

So in this case it will simply be working out the cost of what the extra works (or omitted works) will be or would have been using existing known market rates in accordance with the elements of the schedule of cost components. if it is omitted works, the fact they under-priced it in the first place within the target Price is irrelevant. Equally if the Employer wants more and the Contractor under-priced them then the CE will be based on actual forecast cost not the tendered rate. This will then change the target price up or down, and obviously the Contractor is still paid actual cost under option C so any difference between their tendered rate and the value agreed will come out in the pain/gain calculations.
answered Sep 9, 2018 by Glenn Hide (68,810 points)