Expert advice in minutes not days. Register it's free and ask your first question now.
ReachBack is a free community help desk for construction professionals run by Built Intelligence. A library of high-quality questions from real users with answers delivered and curated by industry experts.

4,951 questions

5,279 answers

1,043 comments

Register its Free

Download here

NEC ECC: Payment under Option C where defined cost is greater than the ToTP

0 votes
230 views
On an ECC Option C contract when assessing the amount due and making payments to a Contractor who is forecasting that at Completion their defined cost will be significantly more than the total of the prices, should payments to the Contractor be capped/limited to the total of the prices or should payments of defined cost continue, exceeding the total of the prices, until completion at which point the Contractor's share is calculated and any overpayment is then repaid by the Contractor?

In my experience it seems to be commonly understood that payments stop once defined cost reaches the ToTP although I can't see that the contract explicitly says that.
asked Sep 3, 2018 in Payment by philjbrady (600 points)  

1 Answer

+2 votes
 
Best answer
I would agree it would be logical that it should be taken into account but that is NOT what the contract says, and I think you mean payments take into account the "pain" share rather than just stop. Contract states that you still pay the Contractor the money and the Client/Employer recovers their share back at the end in the final pain/gain calculation. That does not seem logical to me and I did expect that to be changed in NEC4 but it hasn't.

It is fairly common for a Client/Employer to introduce a Z clause that says once the Prices have been reached then any Client share forecast will be withheld from future payments until the final calculation can be made.  I can fully understand why a Client would include that Z clause, and if I was a Contractor I would not object that was unfair.

For some Clients it may be difficult to recover that some back from the Contractor at that stage so sensible to have withheld it in the first place - but I emphasise it is only the Clients forecast share they are withholding - not all payment.
answered Sep 3, 2018 by Glenn Hide (71,060 points)  
selected Feb 6 by philjbrady