NEC ECC: Contractor finishing beyond Completion Date

+1 vote
202 views
If the Contractor has not achieved completion by the Completion Date am i right i thinking that no 'non-completion' certificate is required?  The Contractor is in culpable delay.
asked Aug 1, 2018 in Time by cnigh1sc (250 points)  

1 Answer

+1 vote
 
Best answer
Yes you are correct in that the Project Manager only certifies (within one week of the date) when Completion has occurred.
answered Aug 2, 2018 by Andrew W-I (17,460 points)  
selected Aug 6, 2018 by Neil Earnshaw