Expert advice in minutes not days. Register it's free and ask your first question now.
ReachBack is a free community help desk for construction professionals run by Built Intelligence. A library of high-quality questions from real users with answers delivered and curated by industry experts.

4,910 questions

5,235 answers

1,011 comments

Register its Free

Download here

NEC ECC: Contractor finishing beyond Completion Date

+1 vote
192 views
If the Contractor has not achieved completion by the Completion Date am i right i thinking that no 'non-completion' certificate is required?  The Contractor is in culpable delay.
asked Aug 1, 2018 in Time by cnigh1sc (220 points)  

1 Answer

+1 vote
 
Best answer
Yes you are correct in that the Project Manager only certifies (within one week of the date) when Completion has occurred.
answered Aug 2, 2018 by Andrew W-I (16,200 points)  
selected Aug 6, 2018 by Neil Earnshaw