NEC ECC: Acceptance of Clause 31 programme

0 votes
47 views
Potentially a daft question;

I have just joined at project where the Clause 31 was recently accepted, and the first CL32 has been submitted.

However, upon inspection, the programme is sub-standard, and fundamentally flawed (I.e. it has taken into account actual Access delays already on site) delaying the programme, plus many other issues relating to compliance (contract dates all wrong, etc).

Even though it has been accepted, can you agree to re-submit  correct one agreed? I’m guessing you shouldn’t, but by mutual agreement you can?

Thanks.
asked Jul 31 in NEC3 Time by KMP2017 (700 points)  

1 Answer

+1 vote
You can't "un-accept" a programme - you can only reject the next one until it reflects what is contractually correct.

However - given that this is the first Accepted Programme that you are going to measure any compensation events against, by agreement you could agree to change it with correct logic if you BOTH agree it was wrong and mutually beneficial to correct
answered Jul 31 by Glenn Hide (61,150 points)