NEC ECC: Subcontracted Fee for ECC Option C

0 votes
61 views
If the Contractor has missed the Subcontract Fee % in ECC Option C contract, during the assessment of CE, can the PM use SSOCC to assess if it is anticipated the Contractor needs to contract out in many CE.
asked Jul 31 in NEC3 Contract Data by Alex Chan (120 points)  

1 Answer

+2 votes
I have understood that there is a Subcontract Fee % stated in CD2.

If it is clear that the Contractor has missed off the Subcontractor fee % within its assessment then the PM, acting impartially, should make the adjustment in considering the quotation. Whether the quotation is acceptable is for the PM to decide.
answered Aug 4 by dave bates (10,220 points)