NEC ECC : Compensation Events for Contractor's Qualifications

+1 vote
163 views
In ECC Option B, can the Contractor subsequently ask for CE 61.3 for his qualification  made in the quotation?
asked Jul 24, 2018 in Compensation Events by acheung (290 points)  

1 Answer

+2 votes
The contract talks about Project Manager assumptions within a quote that can be revisited (as a new CE). There is no where in the contract that says a Contractor assumption or qualification can be revisited.

Therefore I always recommend to Contractors to get PM's to agree assumptions suggested by the Contractor PRIOR to the quotation being issued for acceptance, and otherwise to price the risk instead and accept the quote will be higher.
answered Jul 24, 2018 by Glenn Hide Panel Member (84,440 points)