Expert advice in minutes not days. Register it's free and ask your first question now.
ReachBack is a free community help desk for construction professionals run by Built Intelligence. A library of high-quality questions from real users with answers delivered and curated by industry experts.

4,912 questions

5,237 answers

1,011 comments

Register its Free

Download here

Planning: Can a building with a COI be demolished without any planning application as to its use afterwards

0 votes
58 views
Littlebrook Power Station and chimney have a COI and the owners have obtained a demolition order.   No planning application has been made for its redevelopment but the company have indicated their intentions which once the site is cleared would have difficulty in obtaining planning consent.  However once the site is cleared arguments for alternative use will be futile.  Is this right that a COI can be used to demolish a building without lodging a planning application for its replacement.
asked Jul 15, 2018 in Planning and Architecture by Mack (120 points)  

1 Answer

0 votes
A Certificate of Immunity (COI) guarantees that a building will not be statutorily listed, or a building preservation notice won't be served, for 5 years.

Demolition of a building does not usually require planning consent, except for listed buildings that require listed buildings consent, which is probably why the COI was obtained.

Any intentions for subsequent re-development is a separate matter for which an  application would need to be made to the appropriate planning authority.
answered Aug 9, 2018 by Andrew W-I (16,240 points)