NEC ECC: Can a CE change a sectional Completion Date?

0 votes
141 views
We know a compensation event has the ability of changing the completion date, but in turn, can this also change a sectional completion date?  We are not sure if once in contract, a sectional Completion Date can be changed.
asked Jul 4 in Compensation Events by charlotteking (330 points)  

1 Answer

+2 votes
The rules for a sectional Completion Date are exactly the same as the rules for a Completion Date. That means that an implemented compensation event could move a Sectional Completion Date later (to the right) but only acceleration under clause 36 can ever bring it forward (to the left).
answered Jul 4 by Glenn Hide (65,120 points)