NEC4 ECSC: Sectional Completion in NEC4 ECSC

+1 vote
132 views
Can sectional Completion be incorporated into an Engineering and Construction Short Contract? If so, how?
asked Jun 13, 2018 in Time by SL58 (350 points)  

2 Answers

+2 votes
I think if you are starting need elements like this then you are veering away from a straight forward low risk contract that the short contracts are intended for. Having said that, I can see that it may be straight forward work and you just want it complete in phases, so perfectly feasible that it would work and you don't need to revert to the full ECC.

All you would need to do is add a line into the contract data to state what the sectional completion(s) is(are). I suggest you would also need to look at the wording of X5 and incorporate the elements you need as a Z clause into the contract. You may also need to beef up your definition of Completion to make sure it is clear what needs to be achieved in order to achieve (sectional) Completion. Lastly you will need to make it clear whether the delay damages are the same for the Completion Date and Sectional Completion(s) and if not have separate lines for both.
answered Jun 13, 2018 by Glenn Hide (71,060 points)  
Thanks Glenn, this has been helpful.
0 votes
As a simpler alternative to Glenn's suggestion below - but without contractual 'bite' / recourse of delay damages - you can just specify the area that you want completed earlier as a constraint in the Works Information (under NEC3) / Scope (under NEC4).
answered Jun 14, 2018 by Jon Broome (52,270 points)  
Thanks Jon, this has also been helpful.