What are the possible reasons for changing the Works Information?

+1 vote
347 views

 What are the possible reasons for changing the Works Information?

asked Oct 10, 2012 in Compensation Events by BuiltIntelligence (870 points)  

1 Answer

+1 vote
 
Best answer

There may be many reasons for changing the Works Information. They include changes made in order to eliminate an illegality or impossibility (Clause 18) or to resolve an ambiguity (Clause 17).