Expert advice in minutes not days. Register it's free and ask your first question now.
ReachBack is a free community help desk for construction professionals run by Built Intelligence. A library of high-quality questions from real users with answers delivered and curated by industry experts.

Do you want to update your skills in NEC3, NEC4, JCT, Procurement, CDM or Project management?

Sign up for one of our free online courses.

4,580 questions

4,836 answers

812 comments

Register its Free

Download here

NEC ECC: Acceleration and Completion/Section Date

+1 vote
131 views
Under NEC3 ECC Main Option A (April 2013), the Employer has asked for an acceleration quotation and expects additional costs, but also that the Contract Completion Date and relevant Sectional Completion Dates to now be earlier.

63.3 clearly defines delay to completion. However, the understanding is that neither the Contract Completion Date or Sectional Completion Dates change to earlier dates and can only move to be later in line with planned completion movement ?
asked May 16 in NEC3 General by Yahik (230 points)  

2 Answers

+2 votes
 
Best answer
This is acceleration under clause 36 of the contract. The PM can instruct a quotation for acceleration to achieve an earlier Completion Date or Sectional Completion Date. If the PM accepts that quote then the Completion Date or Sectional Completion is now that earlier date, and the point at which delay damages will be applicable under X7. So yes, these dates can move contractually to the left by accepting the quote. It should be emphasised that acceleration is not a compensation event but a stand alone process. The PM can not make their own assessment of the Contractors acceleration quote.

The Contractors "planned Completion" or "planned Sectional Completion" will then subsequently show where they are in terms of that revised contractual milestone i.e. ahead or behind.
answered May 16 by Glenn Hide (61,050 points)  
selected May 18 by Neil Earnshaw
+1 vote
you are right a CE can only extend the Date(s) however acceleration is an expressed provision, BY AGREEMENT, to shorten the duration and bring the date(s) forward.
answered May 16 by dave bates (10,180 points)