Expert advice in minutes not days. Register it's free and ask your first question now.
ReachBack is a free community help desk for construction professionals run by Built Intelligence. A library of high-quality questions from real users with answers delivered and curated by industry experts.

Do you want to update your skills in NEC3, NEC4, JCT, Procurement, CDM or Project management?

Sign up for one of our free online courses.

4,582 questions

4,839 answers

812 comments

Register its Free

Download here

NEC ECC: Extension of time request by the Contractor, which CE clause?

0 votes
128 views
A Contractor has requested an extension of time, which clauses will this be linked to 30, and 60?
asked May 14 in NEC3 Time by anonymous (1,600 points)  

1 Answer

+2 votes
There is no extension of time clause or reason under 60,1 for it to being one. If you have updated a programme and planned Completion has moved you need to see why it has moved and what the reason for it is, and whether that reason is a compensation event under clause 60.1. For example, was it due to physical conditions under 60.1(12), or lack of access under 60.1(2), or delay in acceptance under 60.1(6).

If it is proven that the delay was down to a reason that the PM agrees was a compensation event, then you can assess the impact within that quotation for both cost and time - and if planned Completion has moved as a direct effect then that quotaion should include prelim type costs as well.
answered May 14 by Glenn Hide (61,150 points)