Expert advice in minutes not days. Register it's free and ask your first question now.
ReachBack is a free community help desk for construction professionals run by Built Intelligence. A library of high-quality questions from real users with answers delivered and curated by industry experts.

Do you want to update your skills in NEC3, NEC4, JCT, Procurement, CDM or Project management?

Sign up for one of our free online courses.

4,665 questions

4,944 answers

852 comments

Register its Free

Download here

NEC ECC: Not agreeing CE change of activity duration as significantly different from tender

0 votes
88 views
Post tender design has provided new/change to information in relation to an activity. Client accepted CE and requested quote and revised programme. Revised programme duration has increase significantly in comparison to tender even though new duration is reasonable. New activity duration is not in proportion to increased value or increased volume of work suggesting tender duration's not realistic.

Can Client reject EOT claim? Can Client insist that new duration's should be similar to tender duration's?
asked May 14 in NEC3 Compensation Events by Mario (210 points)  

2 Answers

+1 vote
In answer to your question  "Can Client insist that new durations should be similar to tender durations?", the answer is "No" as this is not a reason in the contract ... and you don't have EoT claims in the NEC !

The principal clause which governs delays to the Completion DateEoT claims in NEC3 ECC in 63.3 and in NEC4 ECC 63.5 which states "A delay to the Completion Date is assessed as the length of time that, due to the compensation event, planned Completion is later that planned Completion is later than planned Completion in the Accepted Programme."

Therefore the "delay" has to be "due to the compensation event" i.e. if the Contractor got the original timings wrong, that is their liability, but if the work involved "due to the compensation event" is an extra week and it is on the critical path, then that is what the Contractor should get.
answered May 14 by Jon Broome (48,040 points)  
+1 vote
The compensation event should at this stage be assessed on its own merits. Whilst the programme duration's might be a starting point as to what is reasonable, the CE should be assessed as to what the Contractor now believes they will be whilst working as efficiently as possible. If the Contractor knows the works will take longer then programmed then they should show that on the programme. That will be for the CE and original activities. If the CE duration affects planned Completion then they will be entitled to assess that impact and Completion Date would move by the same amount (clause 63.3). Obviously any change to the original planned works would be Contractor liability, but programme should be reflecting reality at any point in time.  

In your example here it is only the duration extension that is relevant due to the CE that is claimable as the movement in Completion date. If the original duration was 20 days but should realistically have been 30 days, and now the CE will mean that it should be 40 days, the CE should be for a ten day movement in Completion Date not 20 days. The idea of the CE is that it should put the Contractor in a no better or worse off position after the CE has been assessed (+ fee).  

If tender duration is known to be wrong then it should not be used to assess a CE - and that is the same if it is a positive or negative difference.
answered May 14 by Glenn Hide (63,870 points)