On an option A contract, the Contract [WI and C. Data] have a number of dates listed for Sectional Completions. However, some of them have been struck out.
However, two months into the contract these [struck-through] elements / Dates were instructed back into the contract.
Am I right in saying that although these should be target dates (in the spirit of collaboration), these new Completion dates are not contractual as there are CE works. To add to this, there should be no risk of LD’s associated with these dates either?