Expert advice in minutes not days. Register it's free and ask your first question now.
ReachBack is a free community help desk for construction professionals run by Built Intelligence. A library of high-quality questions from real users with answers delivered and curated by industry experts.

Do you want to update your skills in NEC3, NEC4, JCT, Procurement, CDM or Project management?

Sign up for one of our free online courses.

4,665 questions

4,944 answers

852 comments

Register its Free

Download here

NEC ECS: Supervision for production related cost when no EOT exists

0 votes
62 views
We are a precast concrete Subcontractor under an option A subcontract. When pricing compensation events that have no EOT, the Contractor is happy to pay for the additional factory labour but not the supervisor and the QA manager. His argument is that these costs are prelims and the Subcontractor do not incur any additional cost and that they will only consider a payment if we had to employ additional staff to carry out the works.

However we feel these are production related costs and the dilemma is the labour are not additional cost either as they are permanent company staff too but the additional work through change means that we have to spend more production time with not just labour but also a supervisor and a QA manager. We believe these costs should be paid for by the Contractor but did not succeed in convincing him to pay for these. Are we correct to assume so? If yes what is the contractual approach to adopt?
asked May 10 in NEC3 Compensation Events by nchibl (150 points)  

1 Answer

+1 vote
 
Best answer
You have to demonstrate that there is a change in Defined Costs (to which you add the Fee). So you have to demonstrate that the supervisor and QA person are directly involved in doing the work i.e. spend more time as a direct result of the compensation event.
answered May 10 by Jon Broome (48,040 points)  
selected May 14 by nchibl