Expert advice in minutes not days. Register it's free and ask your first question now.
ReachBack is a free community help desk for construction professionals run by Built Intelligence. A library of high-quality questions from real users with answers delivered and curated by industry experts.

5,107 questions

5,450 answers

1,170 comments

Register its Free

Download here

NEC ECC: Communication between Project Manager and Contractor

+2 votes
214 views
Can the Contractor communicate with the Client if it is regards to the Project Manager not responding?
asked Apr 12, 2018 in General by Zed (460 points)  

3 Answers

0 votes
 
Best answer
I would like to slightly disagree and say yes absolutely the contractor can communicate with the client. It is critical to remember that the contracting parties are the Client and the Contractor, the PM for all his powers is a creature of the project given specific power and obligations by the Contract but outside those specific powers and obligations the PM is of no relevance to commercial discussions.

This is not a multiparty contract (such as the PPC2000). I do agree however that the right forum is a risk reduction meeting following EWN.
answered Apr 13, 2018 by Rob Horne (19,440 points)  
selected May 10, 2018 by Glenn Hide
+3 votes
Not formally, although you can notify a compensation event under clause 60.1 (6) which should focus the Project Manager's attention.
answered Apr 12, 2018 by Andrew W-I (20,090 points)  
As Andrew says there is no formal procedure for doing this however an informal approach to the Client might work. In addition to notifying the CE as Andrew says, each non-response should also be notified as an early warning if there is likely to be an impact on time, cost or performance as consequence of the lack of response. You can then discuss resolution in a risk reduction meeting with the PM and request that the Client attends also (under clause 16.2).
This is a good suggestion!  Also there is nothing really stopping the contractor from copying in the employer to some correspondence.  The employer would be interested to see if his project manager is not performing in terms of the contract.
0 votes
One other thing I would add to the comments below is that if one of the good NEC cloud based communications systems is being used - with read only access by the Employer- it becomes abundantly clear who is and is not operating the contract properly.
answered Apr 13, 2018 by Jon Broome (54,520 points)