Is clarification of previously issued drawings or specifications a compensation event?

+1 vote
373 views

 Is clarification of previously issued drawings or specifications a compensation event?

asked Oct 10, 2012 in Compensation Events by BuiltIntelligence (870 points)  

1 Answer

+1 vote
 
Best answer

Clarification of previously issued drawings or specifications is only made by changing the Works Information. Therefore, all such clarifications are compensation events although not all of them will lead to additional time or monies (see Clause 60.1(1)).

answered Oct 10, 2012 by BuiltIntelligence (870 points)