Expert advice in minutes not days. Register it's free and ask your first question now.
ReachBack is a free community help desk for construction professionals run by Built Intelligence. A library of high-quality questions from real users with answers delivered and curated by industry experts.

5,429 questions

5,811 answers

1,292 comments

Register its Free

Download here

NEC ECC: Is a signed contract is not physically received by Contractor a CE

0 votes
132 views
An ECC NEC3 contract Option A has been signed by both parties and executed. Although the Contractor was spoken to and told that this was the case a copy of the signed contract did not get issued to him until 2 days after signing.

The contract start date was on the date of signing.

The Contractor has raised an early warning saying this will delay the mobilisation and long lead items.

The access dates to the site are not affected.

He is claiming that this is a compensation event and will delay the works thus leading to additional cost.

Does the non receipt of a signed contract give cause for a CE or have any specific affect under the NEC3?
asked Mar 15, 2018 in Compensation Events by Neil Jeffs (490 points)  

2 Answers

0 votes
 
Best answer
From the Contractor's view, they have to demonstrate that it is a compensation event i.e. satisfy one of the events listed in 60.1. Perhaps the Employer did not provide something he / it should have done in the Accepted Programme ?

Regardless, having passed this hurdle, they then have to demonstrate the effect. Without more details, not sure how I can be more helpful.
answered Mar 16, 2018 by Jon Broome Panel Member (60,890 points)  
selected Mar 17, 2018 by Glenn Hide
0 votes
In short, this is nonsense! BUT next time, as a matter of good practice, I suggest you scan the signature page and send it by email to show contract is properly completed and C is good to go.
answered Mar 16, 2018 by Sarah Schutte (660 points)