NEC ECC: Clause 32 v Clause 62 programmes

+1 vote
472 views
Do both clause 32 & clause 62 programmes need to be accepted?
asked Mar 1, 2018 in Time by KPS1 (250 points)  

1 Answer

+2 votes
 
Best answer
Clause 32 revised programmes have to be accepted/rejected by the Project Manager the same way as the initial clause 31 programme.

Clause 62 programmes (as you call them) are programmes that go with a quotation. They do not become accepted when the quote is accepted - but just help ascertain of the quotation is correct, particularly in terms of entitlement to move Completion Date (or Sectional/Key Dates).

The cumulative effects of any compensation event(s) will simply be shown in the next programme issued for acceptance (under clause 32.1)
answered Mar 1, 2018 by Glenn Hide (70,150 points)  
selected Mar 8, 2018 by Neil Earnshaw