NEC ECC: Clause 32 v Clause 62 programmes

+1 vote
Do both clause 32 & clause 62 programmes need to be accepted?
asked Mar 1 in NEC3 Time by KittyP (220 points)  

1 Answer

+2 votes
Best answer
Clause 32 revised programmes have to be accepted/rejected by the Project Manager the same way as the initial clause 31 programme.

Clause 62 programmes (as you call them) are programmes that go with a quotation. They do not become accepted when the quote is accepted - but just help ascertain of the quotation is correct, particularly in terms of entitlement to move Completion Date (or Sectional/Key Dates).

The cumulative effects of any compensation event(s) will simply be shown in the next programme issued for acceptance (under clause 32.1)
answered Mar 1 by Glenn Hide (56,340 points)  
selected Mar 8 by Neil Earnshaw