NEC PSC: Suitability for a security contractor?

0 votes
63 views
Would a PSC be suitable for a security contractor who is to provide security services for a site which includes security personnel, CCTV equipment and Software ?
asked Feb 13, 2018 in General by QS007 (450 points)  

1 Answer

+1 vote
 
Best answer
For me, probably not as
(a) it is a bit too complex a contract for such a simple service
(b) it is probably not in the realms of a 'professional' service
(c) it is being provided at a location and
(d) physical infrastructure is being provided, so more than just people services.

I would have thought the NEC4 Term Service SHORT Contract would be most suitable.
answered Feb 14, 2018 by Jon Broome (50,870 points)