Expert advice in minutes not days. Register it's free and ask your first question now.
ReachBack is a free community help desk for construction professionals run by Built Intelligence. A library of high-quality questions from real users with answers delivered and curated by industry experts.

5,095 questions

5,437 answers

1,160 comments

Register its Free

Download here

NEC ECC: Paid sleep days after night works

0 votes
612 views
Our client has requested works to be performed at night to limit the effect to their customers. Previously there had all occurred during the week. As a result of these night works they have paid us double time for the night works and then a sleep day the following day.

However recently we have performed some night works but on Saturday and Sundays and the client is now refusing to pay for the sleep day.

Are we due the sleep days? I've checked both our framework agreement with them and our Option E contract, and there is no mention of sleep days in either. So would appreciate any advice
asked Feb 9, 2018 in Main options by Mark Dell (150 points)  

1 Answer

+1 vote
 
Best answer
Under an Option E contract you are paid Defined Cost plus Fees. Defined Cost is a term defined at clause 11.2(23) of the ECC which is broken into three elements (1) payments to Subcontractors, (2) cost of components in the Schedule of Cost Components, and (3) Disallowed Cost.

If your client (presumably the Employer and Project Manager?) doesn't want to pay something as Defined Cost then they would have to justify why by reference to the contract. Is the cost not payable as payments due to Subcontractors? Does the cost not comply with one of the components in the Schedule of Cost Components? Does the cost comply with one of the bullets point under Disallowed Cost?

On your part, you need to demonstrate that the cost you are claiming is actual cost you have paid out usually by provision of an invoice or subcontract payment certificate. You also need to make sure the cost is liable to be paid in accordance with (1) and (2) above and doesn't fall foul of (3). You also have to demonstrate that the amounts you've paid are in accordance with clause 52.1 and are at open market or competitively tendered prices etc etc.

Basically if you have a liability to pay for something as a result of an instruction from the PM, provided you can demonstrate that the cost was incurred and is due for payment under the contract, the Employer / PM doesn't have much of an argument against you. This said I've come across this issue before and you may find getting them to budge on the issue difficult.

Remember in an ECC Option E contract, you the Contractor take very little financial risk, most of the risk is with the Employer and around how they instruct the work they need.
answered Feb 9, 2018 by Neil Earnshaw (21,050 points)