Expert advice in minutes not days. Register it's free and ask your first question now.
ReachBack is our free community help desk for construction professionals. A library of high-quality questions from real users with answers delivered and curated by a panel of industry experts.

4,331 questions

4,533 answers

597 comments

34,883 users

Register its Free

Download here

NEC ECS: Option A, no subcontractor rates have been advised to the main Contractor

0 votes
67 views
An option A contract, no subcontractor schedule or rates have been advised to the main contractor. Late in the project the main contractor is unhappy with our subcontractor cost plus fee and requests we use our rate ( which is less ) for the price of works. Would this still stand at subcontractor cost plus fee?
asked Jan 5 in NEC3 Payment by anonymous (290 points)  
   

1 Answer

0 votes
Can you expand upon the circumstances a bit. E.g. :
- where do these rates come from which the Contractor wants you to use later on in the contract ?
- this is for a compensation event as opposed to original work (which I assume you are being paid for under the activity schedule ) ?
answered Jan 7 by Jon Broome (25,720 points)