NEC ECC: No working area in SSCC?

0 votes
338 views
Why does the Shorter Schedule of Cost Components not include Working Area Overheads?
asked Dec 31, 2017 in NEC3 SOCC SSOCC by anonymous (1,580 points)  

1 Answer

0 votes
 
Best answer
It has the percentage for People overheads instead. This covers the equivalent of the percentage for Working Area overheads AND other items in '4. Charges' of the full Schedule of Cost Components.

The reason for the more extensive coverage is that the Shorter SCC is only used for assessing compensation events under options A and B which should, in theory, be less under these options than under the cost-based options C to F.
answered Jan 1 by Jon Broome (46,260 points)