JCT: Main contractors OHP percentage for Subcontractor priced variations.

+1 vote
773 views
Can you please give me the prescribed method for obtaining the main contractors OHP percentage  for Subcontractor priced variations in JCT ICD11.
In the Daywork Section of this contract, materials and goods OHP are 30% and plant OHP is 10%.
asked Dec 20, 2017 in General by rawhoe07 (160 points)  

1 Answer

+1 vote
 
Best answer
I do not believe there is a "prescribed method". If a percentage is not stated you will need to agree a suitable rate.
answered Feb 20, 2018 by Rob Horne Panel Member (19,700 points)