Expert advice in minutes not days. Register it's free and ask your first question now.
ReachBack is a free community help desk for construction professionals run by Built Intelligence. A library of high-quality questions from real users with answers delivered and curated by industry experts.

Do you want to update your skills in NEC3, NEC4, JCT, Procurement, CDM or Project management?

Sign up for one of our free online courses.

4,457 questions

4,695 answers

711 comments

Register its Free

Download here

NEC ECC: Assessing programme impact of a instruction which includes both a scope increase and decrease.

0 votes
266 views
When assessing the programme impact of a new instruction that includes both a scope increase and reduction, which method should be used (assuming both items are on the critical path):

a) assess the impact of the scope increase and decrease together (i.e partially mitigate each other)
b) assess the impact of the scope increase and decrease separately (i.e increase in terminal float and a delay in completion date)
asked Dec 20, 2017 in NEC3 Time by Kevin Cooper (250 points)  

2 Answers

0 votes
 
Best answer
Option a) would be correct - assess the impact as a whole if it is all part of one event.
answered Dec 20, 2017 by Glenn Hide (57,240 points)  
selected Dec 20, 2017 by Kevin Cooper
0 votes
Kevin,

As Glenn has stated - if it is related to "one event" then yes it should be impacted as one. Assuming the instruction came through as an "addition/ omission of scope" in one instruction/ at the same time.

Regards,

K
answered Jan 5 by KMP2017 (560 points)