Expert advice in minutes not days. Register it's free and ask your first question now.
ReachBack is a free community help desk for construction professionals run by Built Intelligence. A library of high-quality questions from real users with answers delivered and curated by industry experts.

Do you want to update your skills in NEC3, NEC4, JCT, Procurement, CDM or Project management?

Sign up for one of our free online courses.

4,545 questions

4,798 answers

791 comments

Register its Free

Download here

NEC ECC: Take Over at Completion or at point of issue of Completion Certificate?

0 votes
241 views
Clause 30.2 states that the Project Manager decided date of Completion and certifies within one week. However – is it just the paperwork that comes one week later or do they not need to physically take possession of the site back until the issue of that piece of paper one week later?

If the latter, we have some very expensive prelims in terms of security and other costs so should we have allowed for an extra week of that cost within our tender?
asked Dec 18, 2017 in NEC3 Time by anonymous (1,580 points)  

1 Answer

+2 votes
 
Best answer
Usually the PM should state the date of Completion on the certificate which by clause 30.2 might be up to one week before he issues the certificate. The date the certificate was issued is irrelevant other than demonstrating that the PM did in fact issue it within the required time frame.

Note that possession as a concept isn't used in NEC, so the Contractor never has possession and therefore the Employer never takes it back. The Contractor merely has access to the Site (clause 33).

Clause 35 deals with take over, in particular clause 35.1 requires the Employer to take over no later than two weeks after Completion. There is no need for the PM to issue a take over certificate unless the Employer has taken over any part of the works (clause 35.3).

Let's say the PM decides Completion has occurred on the 1st Dec, he has up until the 8th Dec to issue a certificate that states this (clause 30.2) and the Employer must take over by 15th Dec (clause 35.1). The Contractor is liable for loss of or damage to the works, Plant and Materials until the Employer has taken over (clauses 80.1 and 81.1) and as such will need to provide whatever resources are needed to ensure this risk is mitigated e.g. site hoardings, security etc. So yes, potentially you should have allowed something in your tender for the period between Completion and take over but that's a Contractor's risk which you would no doubt take a commercial decision on how to price.
answered Dec 19, 2017 by Neil Earnshaw (15,490 points)