NEC ECC: Shallow underground services in a town centre environment

+1 vote
121 views
On the back of this answer, if you have an experienced Contractor who you have worked with previously on schemes of a similar nature, who came across shallow underground services on those previous jobs, could they then claim that they deemed the occurrence of the same scenario to have such a small chance of occurring this time that they didn't allow for it at tender?  The public utility returns were provided in the Site Information and a statement within the Works Information that unchartered utilities are to be expected within the construction depth as private services to individual premises.
asked Dec 14, 2017 in NEC3 Compensation Events by LA1 (670 points)  

1 Answer

+1 vote
 
Best answer
The context of ‘experienced contractor’ here is of a Contractor making a judgement with regard to the likely occurrence of certain physical conditions.  It follows, therefore, that the ‘experience’ relates to a degree of understanding gained from having previously organised, managed, constructed and delivered works of a similar nature, whether they actually have or not, because that is what the CE clause states.

The reference to ‘small chance of occurring’ is not specifically defined, although the paragraph continues with the inclusion of a test of reasonableness, based on a ‘considered opinion’ from an ‘experienced contractor’.

Consequently, it would seem reasonable to include an allowance where a risk is more likely than not to occur, possibly based on a sliding scale assessment rather than an ‘all or nothing’ principle.

The fact that the Works Information included a statement that 'unchartered utilities are to be expected' does not make this any easier in some ways.  Was it referenced as part of the 'scope'?  If so then this provides a baseline reference level of work.  However, how do you define this as the insertion itself is quite vague about type and location so it is unclear how you would include this, not least in the programme.

What it does do, however, is suggest that services are expected to be encountered so the argument should come down to the last paragraph in clause 60.1 (12) which relates to the 'difference'.

Never an easy CE to deal with and in my experience one of the most subjective, well apart from the weather of course.
answered Dec 15, 2017 by Andrew WI (9,450 points)  
Good points raised by Andrew above. Remember when acting as Project Manager and deciding if this is a compensation event or not you have to be objective and base your decision on the facts available. Also the standard of proof you apply to your decision is "on the balance of probabilities" i.e. that it was more likely than not that the event happened. The fact that the Contractor had come across similar conditions previously is very persuasive, provided that the Contractor had priced the current job after encountering those conditions otherwise he wouldn't have been able to allow for them.